DURAWALL - Do It Yourself !

Recommended Tools:

Post-Hole Shovel - String-line - Spirit Level - Tape Measure - Crow Bar

Method:
  • Set out the post-holes by using your string-line.

  • Measure post hole centres at 1520mm.

  • Dig or bore holes to required depth.

  • Starting at one end, place a post in the hole to the correct depth.

  • Level in bottom sleeper and insert second post.

  • Posts should be plumb laterally, but leaning back as per diagram.

  • Continue until all bottom sleepers are level and well supported.

  • Load up remaining sleepers.

  • Concrete in posts.

  • Wait five (5) days before backfilling.
Note:
  1. Walls above 1000mm require Council Approval.
  2. Technical data for walls 1200 and 1400 high available from DURAWALL.



 
249028


For Business Owners
We're ranked #1 in the Hitwise Australia 'Building and Construction' category.
View awards
Download our iPhone App

Find businesses on the go with the hipages iPhone app.

Partner Sites
No time for the ring around? I can help you
  1. Tell us what you need
  2. We alert local tradies
  3. Tradies contact you
Learn More Now »

Haven't found what you're looking for? Try searching our entire site:

Go